1.The appearance and cleanliness inspection to be pouring equipment;
2 check the construction equipment in good condition, vibrating tools must have complete spare parts;
3 check the anchor type, size, layout and quality of welding, metal anchors must do expansion compensation processing;
4 check the surrounding refractory and heat insulation castable loss prevention measures;
5 check the castable packing and date of manufacture, and pre experiment to check whether the failure;
6 check the construction water, the quality of its water quality must meet the drinking water.